How to compare commercial battery storage quotes

Two quotes at the same price per kWh can describe different batteries. A checklist for comparing usable capacity, power, scope, exclusions and warranty.

Want this modelled for your own site? Get a free feasibility summary in 3 working days →

Two quotes for a commercial battery can carry the same price per kWh and describe different equipment, different scope and different risk. The published figures in our guide to commercial battery storage cost show how wide the ranges are, and the reason is largely what each quote leaves in or out. This post is the checklist for putting quotes on a like-for-like basis before you compare a single price.

Step 1: agree what the kWh and the kW mean

A per-kWh price is only meaningful if everyone is dividing by the same kWh. Ask each bidder to state four numbers in writing:

  1. Nominal energy, the figure on the battery’s datasheet, in kWh.
  2. Usable energy, what you can actually draw after the manufacturer’s limits and any reserve, in kWh, and whether it is measured at the battery or at the point of connection after the inverter.
  3. Continuous power, in kW at the AC output, and whether it can be sustained for the whole duration.
  4. Duration, which is energy divided by power. A 250 kWh battery rated at 125 kW is a two-hour system.

Our guide to kW vs kWh explains the difference between power and energy, and why a battery sized on the wrong one disappoints.

Step 2: an example of how the ranking can flip

These are invented round numbers to show the arithmetic. They are not quotes and not typical prices.

Quote AQuote B
Price before VAT£90,000£92,000
Nominal energy250 kWh240 kWh
Price per nominal kWh£360£383
Usable share of nominal90%95%
Usable energy225 kWh228 kWh
Price per usable kWh£400£404
Includes groundworks and enclosure?NoYes

Quote A looks about 6% cheaper per nominal kWh. Per usable kWh the gap has shrunk to about 1%, and Quote B includes groundworks and an enclosure that Quote A would add as an extra. Comparing on the headline number would have picked the wrong bidder.

Step 3: a scope checklist

Ask each bidder to mark every line as included, excluded or provisional. A quote that cannot be marked up this way is not yet a quote.

ItemWhat to ask
Battery modules and racksCapacity, chemistry, manufacturer and model
Inverter (power conversion system)Rating, efficiency, and whether it is the right size for the kW you need
Battery management and energy management softwareWhat it does, who operates it, and whether it needs a subscription
Enclosure or containerIndoor or outdoor, rating, and whether it is included
Switchgear, protection and cablingWhether your existing board can take it, or the upgrade is priced
Groundworks and civilsBase, fencing, screening and access, for outdoor installations
Fire detection, suppression and ventilationWhat the design is based on, and who signs it off
Metering and monitoringWhat data you will see, and who owns it
Grid connectionWho applies, who pays the network operator, and what happens if reinforcement is required
Commissioning and handoverWhich tests, which documents, and what training
Planning supportFor outdoor installations, who prepares and pays for any application
Operation, maintenance and warrantyWhat is covered, for how long, and what voids it

Step 4: performance and warranty terms

Headline efficiency and life claims are where optimism creeps in. Ask what each figure is measured on, and put the answers beside a neutral benchmark. The US National Renewable Energy Laboratory’s 2024 Annual Technology Baseline uses a round-trip efficiency of 85% and a 15-year lifetime at about one cycle a day for commercial batteries (NREL ATB 2024). That is a modelling assumption, not a promise, but a bidder claiming far better should be able to show the basis.

Step 5: price basis and risk

Questions to ask every bidder

  1. What is the usable energy at the AC point of connection, and the continuous power, in writing?
  2. Which items in the scope checklist are excluded or provisional?
  3. What is the total price including every exclusion you know you will need to add?
  4. What is the warranty throughput, the guaranteed end-of-warranty capacity and the conditions that void it?
  5. Who applies for the grid connection, and who bears the cost if reinforcement is needed?
  6. Who maintains the battery, and what does that cost per year?
  7. What happens to the price, the warranty and the monitoring if the installer or the manufacturer fails?
  8. Are you MCS-certified, NICEIC-registered or a member of another body, and what is the registration number? Check it with the issuing body.

If you would like quotes from installers that meet your own checklist, the free feasibility summary sets out your load and a sensible size so that every bidder starts from the same figures.

Sources

FREE FEASIBILITY

Get the numbers for your own site

This guide is general. The only figure that matters is yours, modelled from your own consumption and tariff.

What you get, within 3 working days: a 2-page battery feasibility summary naming your indicative system size (kW and kWh), the installed cost band, which value streams actually apply to your site (peak-shaving, red-band DUoS avoidance, load shifting, solar self-consumption, grid services), and an honest payback range. If storage does not stack up for your site, the summary says so.

What we will not do
  • We do not run a lead auction. Your details are never sold or passed to a panel of installers.
  • No marketing list, no newsletter sign-up, no unsolicited calls.
  • We will not oversize a system to inflate a quote, or model a payback we cannot defend.

Published by SEO Dons, a specialist commercial energy information network. We are independent: we are not an energy supplier and not a battery manufacturer.

We reply within one working day. Prefer to talk first? +44 7707 970661

Independent guidance for UK commercial sites

  • Independent & supplier-neutral
  • No manufacturer tie-ins
  • UK commercial & industrial sites